CRISPIVORE BEEF FREEZE-DRY TRIAL — WORK SCHEDULE
Job Number: ST104323 | Start Date: 7/1/2025 | Trial Duration: 4 Weeks (28 Days)
PROJECT SCOPE & TARGETS
ParameterValueUnitSource / Notes
Production Target (Bulk Output)250000lbsTask requirement — minimum 250,000 lbs
Output per Freeze Dryer Cycle4620lbsProduct Specification: 7,680 lbs raw → 4,620 lbs finished...
Raw Input per Freeze Dryer Cycle7680lbsProduct Specification: full batch size per dryer
Number of Freeze Dryers2unitsPlan & Establish: 2 dryers available
Freeze Dry Cycle Time15hoursProduct Specification: 15-hour drying cycle per batch
Shift Length12hoursPlan & Establish: 12-hour shifts
Shifts per Day2shiftsPlan & Establish: 24/7 production (2 shifts/day)
Employees per Shift20personsPlan & Establish: 20 personnel per 12-hr shift
Total Employees per Day=B13*2personsCalculated: 2 shifts × 20 employees
Trial Duration28daysTask requirement: four weeks
Start Date7/1/2025datePlan & Establish reference
Raw Waste / Shrinkage Rate0.02%Product Specification: average 2% raw waste
Finished Waste / Shrinkage Rate0.02%Product Specification: average 2% finished waste
Realistic Cycles per Dryer per Day1cyclesOperational assumption: 1 full batch per dryer per day (a...
CALCULATED METRICS & FEASIBILITY
Total Cycles Required (Target)=B6/B7cyclesProduction Target ÷ Output per Cycle
Cycles per Dryer Required=B22/B9cyclesTotal Cycles Required ÷ Number of Dryers
Theoretical Max Cycles per Day (per dryer)=24/B10cycles24 hours ÷ Freeze Dry Cycle Time
Realistic Cycles per Day (per dryer)=B19cyclesOperational assumption (prep + packaging + 15-hr cycle)
Total Cycles Possible (Trial)=B25*B9*B15cyclesRealistic Cycles/Day × Dryers × Days
Total Output Possible (Trial)=B26*B7lbsTotal Cycles Possible × Output per Cycle
Target Achieved?=IF(B27>=B6,"YES — EXCEEDED","NO — NOT MET")Compares Total Output Possible vs Production Target
Margin Above Target=B27-B6lbsTotal Output Possible minus Production Target
Margin Above Target (%)=B29/B6%Margin ÷ Production Target
Total Raw Input Required=B22*B8lbsTotal Cycles Required × Raw Input per Cycle
Total Labor Hours per Cycle=20*4hrs20 employees × avg 4 hrs active per cycle (prep + pack + ...
Total Labor Hours over Trial=B26*B32hrsTotal Cycles Possible × Labor Hours per Cycle
Average Daily Output=B27/B15lbs/dayTotal Output Possible ÷ Trial Duration
Required Daily Output to Meet Target=B6/B15lbs/dayProduction Target ÷ Trial Duration
EQUIPMENT CAPACITY SUMMARY
EquipmentCapacityCycle TimeOperating WindowStagger Strategy
Freeze Dryer 17,680 lbs raw / 4,620 lbs output15 hours24/7Starts Day 1 06:00
Freeze Dryer 27,680 lbs raw / 4,620 lbs output15 hours24/7Starts Day 1 13:30 (7.5-hr stagger)
Packaging Line6 totes per dryer cycle~2.5 hrsPost-dryerRuns after each dryer unload
Freezer StagingFull batch (480 trays)As neededPre-dryerHolds prepped trays before dryer loading
CRISPIVORE BEEF FREEZE-DRY TRIAL — PRODUCTION ASSIGNMENTS
Job Number: ST104323 | 20 Personnel per 12-Hour Shift | 40 Total Personnel per Day (2 Shifts)
Role# per ShiftShift CoveragePrimary ResponsibilitiesKey TasksNotes
Supervisor1Both (rotates weekly)Overall production oversight, shift coordination, safety ...• Leads shift handoff meetings • Approves batch records a...1 per shift; may work overtime during critical load/unloa...
Lead2Both (1 per dryer area)Assist Supervisor in directing floor activities, troubles...• Directs tray prep and loader teams • Coordinates dryer ...2 per shift; ideally 1 dedicated to each dryer zone
Tray Prep / Tray Loader6Both (rotates)Prepare trays, portion meat onto trays, weigh, load onto ...• Inspect and clean trays • Load 16 lbs of raw beef per t...6 per shift; batch size = 480 trays per dryer (7,680 lbs ...
Freeze Dryer Operator2Both (1 per dryer)Operate and monitor freeze dryers, manage load/unload seq...• Load full trolleys into dryer • Set/verify cycle parame...2 per shift; 1 operator assigned to each dryer for contin...
Packaging Operator7Both (rotates)Inspect finished product, perform metal detection, bulk-p...• Inspect finished product (texture, color, moisture) • M...7 per shift; supports 6 totes per dryer cycle (3 totes pe...
QA Technician1Both (rotates)Quality assurance sampling, traceability verification, do...• Collect samples for testing (Salmonella, Listeria, CFU/...1 per shift; critical path for batch release
Maintenance1Both (on-call + rounds)Preventive and corrective maintenance on freeze dryers, p...• Pre-shift equipment inspections • Respond to breakdowns...1 per shift; cross-trained on both dryers
TOTAL PER SHIFT=SUM(B5:B11)Replicated for Shift 2
DAILY LABOR SUMMARY (24-HOUR COVERAGE)
Role# per DayShift 1 (06:00–18:00)Shift 2 (18:00–06:00)Overlap / Handoff
Supervisor=B5*21130-min overlap at shift change for handoff
Lead=B6*22230-min overlap at shift change
Tray Prep / Tray Loader=B7*266Staggered start based on dryer schedule
Freeze Dryer Operator=B8*222Continuous coverage; handoff at mid-cycle if needed
Packaging Operator=B9*277Shift based on dryer unload timing
QA Technician=B10*211Continuous coverage for batch release
Maintenance=B11*211On-call + rounds during both shifts
TOTAL DAILY LABOR=SUM(B16:B22)2020
CRISPIVORE BEEF FREEZE-DRY TRIAL — PRODUCTION SEQUENCES
Job Number: ST104323 | 2 Dryers | 15-Hour Cycle | 7.5-Hour Stagger | 20 Personnel per Shift
SECTION A: MASTER PRODUCTION SEQUENCE (Single Dryer Batch)
Step #Sub-Step / ActivityDryerDurationStart (Hrs from Batch Start)End (Hrs from Batch Start)Personnel AssignedShift / Notes
1Tray Prep: Prepare trays, load 16 lbs raw beef, weigh, lo...2026× Tray Prep / LoaderShift 1 or 2
2Load trolleys into freezer / cold staging0.522.52× Tray Prep / LoaderKeeps product at ≤ -20°F
3Load full trolley into freeze dryer1 or 20.52.532× Freeze Dryer Operator, 1× LeadVerify probe placement (Top/Middle/Bottom)
4Freeze Drying — Monitor temperature, vacuum pressure, cyc...1 or 2153182× Freeze Dryer OperatorContinuous monitoring; 3–5% atmospheric pressure
5Unload dryer / remove dried product trays1 or 20.51818.52× Freeze Dryer OperatorEnd of 15-hr cycle
6Unload trays from trolleys; stage for packaging118.519.56× Tray Prep / Loader, 2× Freeze Dryer OperatorCross-functional support
7Inspection & metal detection0.519.5207× Packaging OperatorTexture, color, metal check
8Bulk pack into sacks; place into cardboard tote boxes120217× Packaging Operator6 full totes per dryer cycle
9Insert corner boards, zip tie sacks, tape tote, label (Pr...0.52121.57× Packaging OperatorLabel includes ST104323
10QC check, bag/label/case pack, documentation0.521.5221× QA Technician, 1× SupervisorBatch record completion
11Sample collection & traceability verification0.52222.51× QA TechnicianSalmonella, Listeria, CFU/g testing
BATCH TOTAL=SUM(D6:D16)
SECTION B: 24-HOUR CONCURRENT TIMELINE (Dryer 1 + Dryer 2...
Time of DayDryer 1 ActivityDryer 2 ActivityShift on DutyPersonnel DeployedDryer 1 Step RefDryer 2 Step RefCritical Notes
06:00 – 08:00Tray Prep (Steps 1–2)Idle / Pre-stagingShift 1 (06:00–18:00)6 Tray LoadersA1–A2Dryer 2 pre-staging begins at 13:30
08:00 – 08:30Load Dryer 1 (Step 3)Idle / Pre-stagingShift 12 Operators + 1 LeadA3Dryer 1 cycle starts
08:30 – 13:30Freeze Dry 1 (Step 4)Tray Prep (Steps 1–2)Shift 12 Operators (Dryer 1); 6 Tray Loaders (Dryer 2)A4A1–A2Dryer 2 prep begins at 13:30
13:30 – 14:00Freeze Dry 1 (Step 4)Load Dryer 2 (Step 3)Shift 12 Operators (Dryer 1); 2 Operators + 1 Lead (Dryer 2)A4A3Dryer 2 cycle starts; stagger = 7.5 hrs
14:00 – 18:00Freeze Dry 1 (Step 4)Freeze Dry 2 (Step 4)Shift 12 Operators (Dryer 1); 2 Operators (Dryer 2)A4A4Both dryers in active cycle
18:00 – 21:00Freeze Dry 1 (Step 4)Freeze Dry 2 (Step 4)Shift 2 (18:00–06:00)2 Operators (Dryer 1); 2 Operators (Dryer 2)A4A4Shift change at 18:00; 30-min overlap
21:00 – 21:30Unload Dryer 1 (Step 5)Freeze Dry 2 (Step 4)Shift 22 Operators (Dryer 1); 2 Operators (Dryer 2)A5A4Dryer 1 cycle ends at 21:00
21:30 – 23:30Unload / Stage Dryer 1 (Steps 6–7)Freeze Dry 2 (Step 4)Shift 26 Tray Loaders + 2 Operators (Dryer 1); 2 Operators (Drye...A6–A7A4Dryer 1 product moves to packaging
23:30 – 02:00Packaging Dryer 1 (Steps 8–9)Freeze Dry 2 (Step 4)Shift 27 Packaging Operators (Dryer 1); 2 Operators (Dryer 2)A8–A9A4Dryer 2 continues drying
02:00 – 03:00QC & Docs Dryer 1 (Steps 10–11)Freeze Dry 2 (Step 4)Shift 21 QA + 1 Supervisor (Dryer 1); 2 Operators (Dryer 2)A10–A11A4Dryer 1 batch release paperwork
03:00 – 03:30Idle / Clean-up Dryer 1Unload Dryer 2 (Step 5)Shift 2Maintenance + 2 Operators (Dryer 1); 2 Operators (Dryer 2)A5Dryer 2 cycle ends at 03:00 (next day)
03:30 – 06:00Prep for next Dryer 1 batch (Steps 1–2)Unload / Stage Dryer 2 (Steps 6–7)Shift 26 Tray Loaders (Dryer 1); 6 Tray Loaders + 2 Operators (D...A1–A2A6–A7Continuous cycle; Shift 2 ends at 06:00
06:00 – 07:00Load Dryer 1 (Step 3)Packaging Dryer 2 (Steps 8–9)Shift 1 (next day)2 Operators + 1 Lead (Dryer 1); 7 Packaging Operators (Dr...A3A8–A9Shift 1 resumes; Dryer 2 packaging
07:00 – 09:30Freeze Dry 1 (Step 4)QC & Docs Dryer 2 (Steps 10–11)Shift 12 Operators (Dryer 1); 1 QA + 1 Supervisor (Dryer 2)A4A10–A11Dryer 2 batch release
09:30 – 10:00Freeze Dry 1 (Step 4)Idle / Clean-up Dryer 2Shift 12 Operators (Dryer 1); Maintenance (Dryer 2)A4Dryer 2 ready for next load at 13:30
SECTION C: THROUGHPUT OPTIMIZATION & BOTTLENECK ANALYSIS
ResourceCapacity per CycleUtilizationBottleneck RiskMitigation Strategy
Freeze Dryer 11 batch / 15 hrsHighLowStaggered start prevents queue buildup
Freeze Dryer 21 batch / 15 hrsHighLow7.5-hr stagger balances unload/packaging load
Tray Prep Team (6)480 trays / 2 hrsMediumMediumPre-stage trays; parallel prep if 2nd batch needed
Packaging Team (7)6 totes / 2.5 hrsMediumMediumOverlap packaging with next dryer cycle
QA Technician (1)1 batch release / 0.5 hrsLowHighPre-schedule sampling; use Lead for preliminary checks
Maintenance (1)Continuous roundsLowMediumPM schedule during low-activity windows
Supervisor (1)Continuous oversightLowLowDigital batch records reduce admin burden